Transport for NSW provided Lismore City Council with a dedicated project manager to support recovery efforts, including to facilitate direct negotiations with NSW Reconstruction Authority to support the assessment and approval process. The specialist project manager did not project manage individual road restoration projects.
The extent of damage to the Lismore road and bridge infrastructure is substantial and a major project approach has been required to facilitate the necessary works. Accordingly, the following assistance has been provided:
• established a multi-disciplinary project team to lead the major recovery effort
• completed necessary temporary works to re-establish access for dislocated communities
• established concept designs and investigations to scope the significant reconstruction works
• completed submissions to satisfy the Disaster Recovery Funding Arrangements and establish the funding necessary to facilitate the works.