1236 - Roads, Maritime and Freight - HABERFIELD TO ST PETERS INTERCHANGE

Mookhey, Daniel to the Minister for Roads, Maritime and Freight, and Vice-President of the Executive Council
  1. Concerning the connection from the tunnel between Haberfield to St Peters Interchanges to the Rozelle interchange part of stage 3 of Westconnex:
    1. What is the total expected cost?
    2. What is the finish date?
Answer -

I am advised:

The estimated cost of the full M4-M5 Link (including the Rozelle Interchange) will be $7.2 billion.

The project is in the planning stages and further refinements to actual costs (in relation to particular parts of the M4-M5 Link) will be determined during the procurement process to be carried out in 2017.

The connection from the tunnel between Haberfield to St Peters Interchanges to the Rozelle Interchange is expected to be completed within the existing project schedule in 2023.


Question asked on 17 November 2016 (session 56-1) and published in Questions & Answers Paper No. 89
Answer received on 22 December 2016 and published in Questions & Answers Paper No. 90