Mookhey, Daniel to the
Minister for Roads, Maritime and Freight, and Vice-President of the Executive Council
|
- Are there any penalties levelled on freight trains if they breakdown on the
Sydney Trains network?
- What are the penalties for freight train operators whose trains cause
delays to other trains on the Sydney Trains Network?
- If so what was the total amount of penalties issued in;
- 2015?
- 2014?
- 2013?
- 2012?
- 2011?
- How many times did freight trains cause delays on the Sydney Trains Network
in:
- 2015?
- 2014?
- 2013?
- 2012?
- 2011?
- Has the Government received any advice regarding the introduction of
penalties for delays caused by freight trains?
|
Answer -
|
- No
- Not applicable
- Not applicable
- Since data became available when Sydney Trains was formed on 1 July 2013,
freight trains impacted peak services:
- 31 times in 2015
- 24 times in 2014
- 15 times in the six months from 1 July 2013
- No. The NSW Government works with all parties to maximise on-time
performance and minimise delays.
|
|
Question asked on 23 February 2016 (session 56-1)
and published in
Questions & Answers Paper No. 42
|
Answer received on 29 March 2016
and published in
Questions & Answers Paper No. 54
|