1966 - M4 EAST TUNNEL AND M4 WIDENING

Leong, Jenny to the Minister for Transport and Infrastructure representing the Minister for Roads, Maritime and Freight, and Vice-President of the Executive Council
  1. Has there been, or will there be, concurrent construction of the M4 East tunnel at the same time as the current M4 widening?
    1. Is this occurring now?
    2. Over what period would any overlap occur?
    3. If so, under what authority or approval is this work occurring?
Answer -

I am advised:

Work on the M4 Widening began in March 2015 and is expected to be completed in 2017. Subject to planning approval by the Minister for Planning, work is due to begin on the M4 East in 2016 and due to open to traffic in 2019. All project dates are available on the WestConnex website.

Question asked on 12 November 2015 (session 56-1) and printed in Questions & Answers Paper No. 43
Answer received on 17 December 2015 and to be printed in Questions & Answers Paper No. 48