4377 - M5 MOTORWAY WESTBOUND TRAFFIC UPGRADE UPDATE

Key details

Asking member:
Tina Ayyad
Addressed to portfolio:
Roads
Minister responsible:
Special Minister of State, Minister for Transport, Minister for Roads, Minister for the Arts, Minister for Music and the Night-time Economy, and Minister for Jobs and Tourism
Representing minister:
Minister for Regional Transport and Roads
Asked on:
Wed 12 February 2025
Answer received on:
Wed 19 March 2025
Question published in:
Question and Answers Paper No. 94
Question

Can the Minister provide an update on the M5 Motorway Westbound Traffic Upgrade between Moorebank Avenue and Hume Highway?

Answer

I am advised:

On 24 April 2024, Transport for NSW invited qualified organisations to formally register their interest to design and construct the M5 Westbound Traffic Upgrade project in a two-step procurement.

On 18 October 2024, Transport for NSW invited shortlisted organisations to tender bids in this second stage. The Request for Tender closed on 21 February 2025 and Transport for NSW are currently assessing tender bids.

It is anticipated that the Project will be awarded its major works contract around mid-2025, with construction expected to commence in early 2026, pending the finalisation of the contract.